MSD Home | Construction Contracts | Upcoming Projects | Projects on Sale | Bid Results
This project has been bid and the construction contract is being processed. For bidding/contract details or information on the contract status, please contact Mary Mount of Contract Administration at (513) 244-1383. For project-specific details, please contact the Project Manager at the number listed in the table below.
Bid Results
|
Project Name |
Muddy Creek WWTP Secondary Flow Enhancement and Influent/Effluent Pumping |
|
Sewer No. |
4877 & 5772 |
|
CIP No. |
98-09 & 2006-36 |
|
Bid Opened |
06/05/2007 |
|
Project Type |
WWTP |
|
Low Bidder |
PAE & Associates |
|
Low Bid (Codes) |
$8,395,000.00 (G) |
|
Estimate |
$10,930,000.00 |
|
Contract Status |
Contract Processing |
|
Project Manager |
William Lutz, WWE @ (513) 244-5102 |
|
Time to Complete |
Twenty-eight (28) months after contract award completed |
|
Code |
Contractor Type |
|
G |
General Contractor |
|
P |
Plumbing Contractor |
|
H |
HVAC (mechanical) Contractor |
|
E |
Electrical Contractor |
|
C |
Combined bid (G+H/P/E) Contractor |
The msdgc.org site is a service of the MSD IT Group | Legal Notices | Page last updated July 19, 2007, by Mary Mount.