This project has been bid and the construction contract is being processed. For bidding/contract details or information on the contract status, please contact the Contract Administrator listed in the table below. For project-specific details, please contact the Project Manager at the number listed in the table below.
Bid Results
|
Project Name |
Trenchless Technology Sewer Rehabilitation |
|
Project ID |
10180100 |
|
Bid Opened |
04/24/2008 |
|
Project Type |
Trenchless Technology |
|
Low Bidder |
Reynolds Inliner, LLC |
|
Low Bid |
$3,176,872.60 (General Contractor) |
|
Legislated Amount |
$3,719,342.00 |
|
Contract Status |
Contract Complete |
|
Project Manager |
Eric Saylor @ |
|
Contract
Administrator |
Mary Mount, 513-244-1383 |
|
Time to Complete |
Nine months after contract award |